GCC Platform Migration Project Plan
Project Start Date: Mon 5/1/06
Project Finish Date: Mon 12/25/06
Name | Start_Date | Finish_Date |
|---|---|---|
GCC Platform Migration Project Plan | Mon 5/1/06 | Mon 12/25/06 |
GCC Migration Project commences | Mon 5/1/06 | Mon 5/1/06 |
GCC Project Tasks | Mon 5/1/06 | Mon 12/25/06 |
Project Management | Mon 5/22/06 | Thu 8/31/06 |
Weekly SOP / SLA Status Meetings | Mon 5/22/06 | Thu 8/31/06 |
Weekly Project Status Meetings | Mon 5/22/06 | Fri 7/28/06 |
Project Technical Tasks, Activities, Implementation Timelines, and Deployment | Mon 5/1/06 | Mon 12/25/06 |
Network (KC) | Mon 5/1/06 | Mon 12/25/06 |
New IP schema and VLAN design | Mon 5/1/06 | Thu 5/18/06 |
Computer room network built (VLAN / IP Range) | Fri 5/12/06 | Fri 5/12/06 |
Cutover to new IP address space | Fri 5/12/06 | Fri 5/12/06 |
KC on vacation | Wed 5/31/06 | Fri 6/9/06 |
New Firewall FWSM installed | Mon 5/1/06 | Wed 6/14/06 |
Acquire software licensing for Cisco Firewall | Mon 5/1/06 | Fri 5/26/06 |
FWSM Installed | Mon 5/29/06 | Wed 5/31/06 |
FWSM Configured | Thu 6/1/06 | Fri 6/9/06 |
FWSM Tested | Mon 6/12/06 | Wed 6/14/06 |
New Equipment / Server naming standard finalized | Thu 6/1/06 | Thu 6/22/06 |
VPN Solution | Mon 6/5/06 | Fri 6/23/06 |
Investigate new VPN solution | Mon 6/5/06 | Fri 6/9/06 |
Implement new VPN solution | Mon 6/12/06 | Mon 6/19/06 |
Test VPN | Wed 6/21/06 | Fri 6/23/06 |
Investigate NMS solution / make purchasing decision | Mon 6/5/06 | Fri 6/30/06 |
New VLAN deployment | Wed 5/31/06 | Wed 5/31/06 |
New IP scheme fully implemented (based on edge switch findings) | Wed 5/31/06 | Wed 5/31/06 |
Old VLAN and IP address space decommissioned (based on edge switch findings) | Wed 5/31/06 | Wed 5/31/06 |
Workstation re-addressing | Fri 6/30/06 | Fri 8/11/06 |
Pilot - move switch ports to new VLAN / begin workstation imaging | Fri 6/30/06 | Fri 6/30/06 |
Production - move switch ports to new VLAN / begin workstation imaging | Mon 8/7/06 | Fri 8/11/06 |
All network related documentation to be completed | Mon 7/3/06 | Fri 7/14/06 |
Remove all old IP's and VLAN's from network | Mon 12/25/06 | Mon 12/25/06 |
Network infrastructure complete | Mon 12/25/06 | Mon 12/25/06 |
Active Directory (Cyril) | Mon 5/8/06 | Fri 6/23/06 |
Two DC's built for Lab / Testing use | Mon 5/8/06 | Tue 5/16/06 |
Complete draft of workstation policies, scripts, and OU hierarchy | Wed 5/17/06 | Wed 5/31/06 |
All GPO's fully documented (using VMware GSX) | Thu 6/1/06 | Thu 6/1/06 |
Sandbox AD environment (all four DC servers) with sample OU's operational | Wed 5/17/06 | Thu 6/1/06 |
Testing backup / restore / authoritative restore of AD | Wed 6/21/06 | Fri 6/23/06 |
GPO's fully revised, tested, and finalized | Fri 6/2/06 | Fri 6/23/06 |
Domain Controllers rebuilt for production use | Mon 6/26/06 | Fri 7/14/06 |
All four DC rebuilt for production use | Mon 6/26/06 | Fri 6/30/06 |
All GPO, Scripts, OU's, and DFS recreated | Mon 6/26/06 | Mon 6/26/06 |
Static DNS entries created in AD DNS for non-MS systems | Tue 6/27/06 | Tue 6/27/06 |
Domain production ready | Thu 6/29/06 | Thu 6/29/06 |
Domain Controller and Active Directory documentation completed | Mon 7/3/06 | Fri 7/14/06 |
Active Directory complete | Fri 7/14/06 | Fri 7/14/06 |
SAN / NAS Storage (Rich) | Mon 5/8/06 | Fri 8/11/06 |
SAN / NAS (Rich) | Mon 5/8/06 | Fri 6/23/06 |
Dell/EMC SAN/NAS NS350 quote | Mon 5/8/06 | Wed 5/10/06 |
Two (2) ESX Servers quote | Mon 5/8/06 | Wed 5/10/06 |
Visual inspection / Inventory of black boxes | Mon 5/8/06 | Fri 5/12/06 |
List of systems that will be migrated to NAS/SAN | Mon 5/8/06 | Wed 5/31/06 |
SAN / NAS Implementation | Fri 5/12/06 | Thu 6/15/06 |
SAN / NAS purchased | Fri 5/12/06 | Fri 5/12/06 |
SAN System | Mon 5/22/06 | Wed 6/7/06 |
SAN installed (by EMC) | Mon 5/22/06 | Fri 5/26/06 |
SAN testing | Mon 5/29/06 | Wed 6/7/06 |
SAN ready for production use | Wed 6/7/06 | Wed 6/7/06 |
NAS System | Mon 6/5/06 | Thu 6/15/06 |
NAS file severs built | Mon 6/5/06 | Fri 6/9/06 |
NAS testing | Mon 6/12/06 | Thu 6/15/06 |
NAS ready for production use | Thu 6/15/06 | Thu 6/15/06 |
SAN / NAS documentation to be completed | Thu 6/15/06 | Thu 6/22/06 |
SAN / NAS complete | Fri 6/23/06 | Fri 6/23/06 |
SAN / NAS Back-Up / DR System (Rich) | Mon 5/8/06 | Tue 8/1/06 |
Backup retention recommendations (draft) ready for director review | Mon 5/8/06 | Tue 5/9/06 |
Back-up / restoration hardware and software selection | Mon 5/8/06 | Tue 5/16/06 |
Process for off site storage | Wed 5/31/06 | Wed 5/31/06 |
Determine Server restoration priority | Wed 5/31/06 | Wed 5/31/06 |
Backup server / library installation and configuration | Mon 6/12/06 | Fri 6/16/06 |
Backup server / library testing | Mon 6/19/06 | Fri 6/30/06 |
New backup library and software ready for production use | Mon 7/3/06 | Mon 7/3/06 |
SAN / NAS Back-up documentation / DR Plan to be completed | Thu 7/6/06 | Fri 7/21/06 |
Training on the backup hardware / software | Mon 7/24/06 | Tue 7/25/06 |
SAN / NAS Back-Up / DR System complete | Tue 8/1/06 | Tue 8/1/06 |
ESX Server System (Rich / Dale / Steve) | Mon 5/8/06 | Fri 8/11/06 |
List of systems targeted for migration to ESX system | Mon 5/8/06 | Wed 5/31/06 |
Receive ESX hardware | Mon 6/5/06 | Mon 6/5/06 |
Build DEV ESX | Tue 6/6/06 | Wed 6/7/06 |
Build Production ESX | Fri 6/9/06 | Mon 6/12/06 |
ESX Testing | Mon 6/12/06 | Fri 6/30/06 |
ESX server ready for production use | Mon 7/3/06 | Wed 7/5/06 |
ESX infrastructure to be documented | Thu 7/6/06 | Fri 7/21/06 |
ESX training | Tue 8/1/06 | Fri 8/11/06 |
ESX Server complete | Tue 8/1/06 | Tue 8/1/06 |
SAN / NAS / ESX Migration Plan (KC / Rich / Mark / Teresa) | Mon 6/5/06 | Thu 8/3/06 |
Academic server migration plan (KC / Rich) | Mon 6/5/06 | Fri 6/16/06 |
Administrative server migration plan (KC / Rich) | Mon 6/19/06 | Thu 8/3/06 |
ESX Migration Plan Complete | Thu 8/3/06 | Thu 8/3/06 |
Storage (compiled from all sections) documentation completed | Mon 8/7/06 | Fri 8/11/06 |
Storage complete | Fri 8/11/06 | Fri 8/11/06 |
Change Control (Rich) | Wed 5/31/06 | Fri 8/11/06 |
Change management policy defined | Wed 5/31/06 | Wed 5/31/06 |
Build prototype v1 Change Management system | Thu 6/1/06 | Fri 6/9/06 |
Demo Change Management system prototype | Mon 6/12/06 | Mon 6/12/06 |
Receive team input for Change Management system RFC | Tue 6/13/06 | Mon 6/19/06 |
Build Change Management system prototype v2 with RFC changes | Tue 6/20/06 | Mon 7/3/06 |
Demo Change Management system v2 prototype | Tue 7/4/06 | Tue 7/11/06 |
Update change management policy based on feedback from IT staff | Wed 7/12/06 | Tue 7/25/06 |
Submit Change Management policy for director approval | Wed 7/26/06 | Wed 7/26/06 |
Build online web based, database driven, Change Management on ESX platform | Thu 7/27/06 | Tue 8/1/06 |
Build web page to request CM reports | Tue 8/1/06 | Mon 8/7/06 |
Change Management system available in production | Mon 8/7/06 | Mon 8/7/06 |
Change Management system to be documented | Tue 8/1/06 | Fri 8/11/06 |
Change Control complete | Fri 8/11/06 | Fri 8/11/06 |
Workstation (Roger / Josh) | Mon 5/1/06 | Thu 8/24/06 |
Symantec SAV Corporate Edition server (Preston) | Mon 5/1/06 | Mon 5/8/06 |
SoftGrid® training | Mon 5/22/06 | Fri 5/26/06 |
Macintosh environment / image build | Thu 6/1/06 | Fri 6/30/06 |
AdmitMac testing | Thu 6/1/06 | Fri 6/9/06 |
Mac Print environment testing | Mon 6/12/06 | Tue 6/20/06 |
Logon script / home directory & share testing | Wed 6/21/06 | Fri 6/30/06 |
Production SoftGrid® server implementation | Fri 5/12/06 | Fri 6/30/06 |
Build SoftGrid® Servers | Fri 5/12/06 | Fri 5/19/06 |
Begin importing sequenced apps | Mon 5/22/06 | Fri 5/26/06 |
Modify XML file for imported apps | Mon 5/22/06 | Fri 5/26/06 |
Begin testing of application provisioning using SoftGrid® and Genesis | Mon 5/22/06 | Wed 5/31/06 |
Continue to sequence SoftGrid® 'homed' applications | Mon 5/22/06 | Thu 6/22/06 |
Remove SoftGrid® servers from domain | Fri 6/23/06 | Fri 6/23/06 |
Rejoin SoftGrid® servers to new production domain | Wed 6/28/06 | Wed 6/28/06 |
Recreate groups and service accounts in production domain | Thu 6/29/06 | Thu 6/29/06 |
SoftGrid® documentation to be completed | Mon 6/19/06 | Fri 6/30/06 |
Pilot systems imaged | Fri 6/30/06 | Fri 6/30/06 |
Full workstation, application, and profile testing completed | Fri 6/30/06 | Fri 6/30/06 |
Remaining workstation systems imaged for production use | Fri 8/4/06 | Mon 8/7/06 |
Update workstation image based on pilot findings | Mon 7/31/06 | Fri 8/4/06 |
New workstation image to be documented | Mon 8/14/06 | Thu 8/24/06 |
Workstation requirements complete | Thu 8/24/06 | Thu 8/24/06 |
CDS (Theresa / Mark) | Wed 5/10/06 | Fri 7/7/06 |
Develop new Genesis server on 'Genesissy' development test server | Thu 5/11/06 | Fri 6/23/06 |
Bring up new Genesissy server on test hardware | Thu 5/11/06 | Fri 5/12/06 |
Compile code and move to test server | Tue 5/16/06 | Tue 5/16/06 |
Modify code to use existing remote oracle DB | Thu 5/18/06 | Fri 5/19/06 |
Point to PALDREAM test domain | Mon 5/22/06 | Mon 5/22/06 |
Add LUA libraries | Tue 5/23/06 | Tue 5/23/06 |
Teresa on Vacation | Mon 5/29/06 | Fri 6/2/06 |
Build Apache authentication modules | Mon 6/12/06 | Mon 6/19/06 |
Harden Genisissy test server | Wed 6/21/06 | Fri 6/23/06 |
Document Genisissy test server settings and configuration | Wed 6/21/06 | Fri 6/23/06 |
New Genesis Production System | Wed 5/10/06 | Fri 7/7/06 |
Find server for new Genesis Front End | Wed 5/10/06 | Fri 5/12/06 |
Find server for new CDS oracle DB Back End | Wed 5/10/06 | Fri 5/12/06 |
Build Front End Genesis server | Mon 6/26/06 | Thu 6/29/06 |
Build Back End Oracle Database server | Mon 6/26/06 | Thu 6/29/06 |
Document new Genesis production server settings and configuration | Mon 7/3/06 | Fri 7/7/06 |
CSD complete | Fri 7/7/06 | Fri 7/7/06 |
File System (Mark) | Mon 5/22/06 | Fri 7/14/06 |
Create DFS roots on lab DC's | Mon 5/22/06 | Mon 5/22/06 |
DFS fully tested in Lab | Tue 5/23/06 | Mon 5/29/06 |
Create Genesis script that sets home directory, ACL's, and quotas | Mon 5/22/06 | Fri 5/26/06 |
DFS tested with AD and SAN / NAS | Mon 6/12/06 | Fri 6/16/06 |
Create logon script that maps users to printers based on MAC address or OU | Mon 6/5/06 | Fri 6/9/06 |
Configure IIS to allow remote access to file systems | Mon 5/29/06 | Fri 6/2/06 |
Resolve URL name conflicts | Mon 6/5/06 | Fri 6/9/06 |
decide on Novell File server migration strategy | Mon 5/29/06 | Fri 6/2/06 |
Create script to migrate user data from Novell to NAS | Mon 6/12/06 | Fri 6/16/06 |
NetWare server data and mappings migrated to the NAS/SAN | Mon 6/19/06 | Fri 6/30/06 |
Create DFS roots on production DC's | Wed 6/28/06 | Wed 6/28/06 |
update code/script for production use | Wed 6/28/06 | Wed 6/28/06 |
Document migration sources / destinations | Mon 7/10/06 | Fri 7/14/06 |
Document File System / DFS environment | Mon 7/10/06 | Fri 7/14/06 |
File System complete | Fri 6/23/06 | Fri 6/23/06 |
Printing (Josh) | Mon 5/15/06 | Fri 7/7/06 |
Print server built with printers configured for each model | Mon 5/15/06 | Wed 5/31/06 |
OU based printer mapping logon script | Mon 6/12/06 | Fri 6/23/06 |
Printer server joined to production domain | Tue 6/27/06 | Tue 6/27/06 |
Document Print environment / print servers | Wed 6/28/06 | Fri 7/7/06 |
Josh on Vacation | Wed 7/5/06 | Fri 7/7/06 |
Management requirements complete | Fri 7/7/06 | Fri 7/7/06 |
Security (Steve) | Mon 5/15/06 | Fri 8/4/06 |
Create testing methodology for IPS | Mon 5/15/06 | Fri 5/19/06 |
Use Nessus / NMAP to scan lab/test servers | Mon 6/5/06 | Wed 6/7/06 |
Install / evaluate e-Eye digital Blink IPS on test DC's | Thu 6/8/06 | Mon 6/12/06 |
Host Integrity monitoring using Osiris product | Tue 6/13/06 | Mon 6/19/06 |
Install Osiris on DC, name servers, and student email server | Tue 6/13/06 | Wed 6/14/06 |
Osiris testing | Tue 6/13/06 | Mon 6/19/06 |
Review AD GPO's prior to GPO finalization | Mon 6/5/06 | Fri 6/9/06 |
Assist with firewall implementation | Mon 6/12/06 | Wed 7/5/06 |
Firewall configuration | Mon 6/12/06 | Wed 6/21/06 |
Firewall testing | Thu 6/22/06 | Wed 6/28/06 |
Document Firewall wall security settings | Thu 6/29/06 | Wed 7/5/06 |
Investigate Linux LDAP authentication back to AD (with Dale) | Thu 6/15/06 | Mon 6/19/06 |
Decision point for centralized authentication of host systems | Mon 6/19/06 | Mon 6/19/06 |
Investigate / evaluate Cisco ACS product for centralized network device authentication | Mon 6/19/06 | Fri 6/23/06 |
Use Nessus / NMAP to scan new Production DC's and other servers | Wed 6/28/06 | Thu 6/29/06 |
Acceptable Draft submission to Director | Mon 7/10/06 | Wed 7/12/06 |
Investigate server monitoring and event log reporting products | Mon 7/3/06 | Fri 7/28/06 |
GFI server monitor | Mon 7/3/06 | Fri 7/7/06 |
Net crunch | Mon 7/3/06 | Fri 7/7/06 |
Recommend product for purchase | Mon 7/10/06 | Mon 7/10/06 |
Implement product | Mon 7/24/06 | Fri 7/28/06 |
Document Product implementation | Mon 7/24/06 | Fri 7/28/06 |
Document security configurations / settings / environment | Mon 7/24/06 | Fri 7/28/06 |
Steve on Vacation | Mon 5/22/06 | Fri 6/2/06 |
Black Hat Training | Mon 7/31/06 | Fri 8/4/06 |
Security requirements complete | Fri 8/4/06 | Fri 8/4/06 |
Communications (Amber) | Mon 5/15/06 | Wed 8/16/06 |
Schedule 2x per week SOP / SLA meetings (now through Aug 8th) | Mon 5/15/06 | Fri 5/19/06 |
Task groups to produce SOP (now through July 11th) | Mon 5/15/06 | Fri 5/19/06 |
Create / submit newsletter that highlights the changes made and new features of the network | Mon 6/26/06 | Mon 6/26/06 |
Task groups to produce SLA (July 11th through Aug 8th) | Tue 7/11/06 | Tue 8/8/06 |
Technology Admin Services | Tue 7/11/06 | Tue 8/8/06 |
Technical Support Services * | Tue 7/11/06 | Tue 8/8/06 |
Client Information Services * | Tue 7/11/06 | Tue 8/8/06 |
Systems Architect & Engineering | Tue 7/11/06 | Tue 8/8/06 |
Technology Infrastructure | Tue 7/11/06 | Tue 8/8/06 |
Clean up and finalize SOP | Tue 7/11/06 | Fri 7/14/06 |
Create / submit newsletter that highlights the changes made and new features of the network | Mon 7/17/06 | Mon 7/17/06 |
Clean up and finalize SLA | Tue 8/8/06 | Sun 8/13/06 |
Create / submit newsletter that highlights the changes made and new features of the network | Mon 8/14/06 | Mon 8/14/06 |
Submit SLA to KC for review | Mon 8/14/06 | Mon 8/14/06 |
Submit SLA to Directors for review | Wed 8/16/06 | Wed 8/16/06 |
Communications requirements complete | Wed 8/16/06 | Wed 8/16/06 |
GCC Project Tasks Complete | Mon 12/25/06 | Mon 12/25/06 |